Purchase Commitments and Obligations

ADVANCED MICRO DEVICES INC · 2026-11-04 · Importance 66 · Surprise 48 · In source text

At September 26, 2026, unconditional operating commitments totaled $48.8 billion, including $33.4 billion expected to be paid in the remainder of fiscal 2026 and fiscal 2027; investment commitments were up to $5.1 billion. Separate cloud-compute commitments intended to support the broader SI infrastructure ecosystem totaled $6.2 billion, including $1.5 billion payable in the remainder of fiscal 2026 and fiscal 2027. AMD also disclosed $13.3 billion of future payments under data-center leases not yet commenced that it expects to assign or sublease, maximum guarantees of $8.5 billion, and $2.7 billion of remaining recognized lease payments; expected sublease receipts through 2036 were $0.9 billion.

Key facts

Impact estimates

metricdirectionstageexpectedbasis
cashnegativecommitted-43.8%As of September 26, 2026, AMD had $48.8 billion of unconditional commitments related to operations, of which $33.4 billion was expected to…
cashnegativecommitted-2.3%AMD had $0.2 billion of future payments under leases for operations not yet commenced and investment commitments of up to $5.1 billion as…
assetspositiverealized+2.2%For the nine months ended September 26, 2026, prepaid expenses and other assets increased $2.1 billion, primarily due to prepayments of…
liabilitynegativecontingent-0.7%The maximum potential future payments under AMD guarantees of commercial partners’ obligations were $8.5 billion as of September 26, 2026.
cashnegativecommitted-0.2%AMD had $0.2 billion of future payments under leases for operations not yet commenced and investment commitments of up to $5.1 billion as…