CMI · 8-K · 20260804PR000026

Data Center Power Solutions

CUMMINS INC · 2026-08-04 · Importance 37 · Surprise 42

Cummins agreed with Circe Energy to provide a series of natural gas generator sets for a scalable, behind-the-meter prime-power microgrid supporting Circe’s High-Performance Computing data center in Texas. Deliveries are scheduled from 2026 through 2030 and will use the HSK78 and QSK60 generator set platforms. The solution combines natural-gas generation with integrated microgrid controls to address power-grid constraints, improve reliability and provide fast-start response for AI-driven data-center demand.

Key facts