Willow Project Development

CONOCOPHILLIPS · 2026-11-05 · Importance 50 · Surprise 24 · In source text

Management said Willow remains on track for first oil in early 2029 and that process-module fabrication on the Gulf Coast had exceeded 75% completion, with fabrication expected to finish in the second quarter before modules are shipped to Alaska in summer. The company plans to drill roughly four exploration wells and acquire additional seismic in the coming winter season; it has received federal permits to begin that drilling program. The exploration is intended to identify satellite opportunities that can use Willow infrastructure after the project comes off plateau, with management expecting Willow capital to decline even while exploring and developing satellites.