ES · 10-Q · 2026Q3 · Full report

Revolution Wind Charge

EVERSOURCE ENERGY · 2026-11-06 · Importance 43 · Surprise 42 · From source text

Eversource recorded a $194 million pre-tax charge, or $164.0 million after tax, in the second quarter of 2026 to increase its contingent liability for expected payments to Global Infrastructure Partners (GIP) under the Revolution Wind sale agreement. The charge followed a $284 million pre-tax increase in the third quarter of 2025, partially offset by $209 million of tax benefits, resulting in a $75.0 million after-tax charge in that quarter. The contingent liability was $409.2 million at September 30, 2026, compared with $448.2 million at December 31, 2025; payments during the first nine months of 2026 totaled $233.0 million. Project owners announced construction completion in November 2026, and the post-closing adjustment reconciliation is expected in 2027.

Key facts

Impact estimates

metricdirectionstageexpectedbasis
cashunclearcontingent—Revolution Wind construction was announced complete in November 2026; the post-closing adjustment reconciliation with GIP is expected in…
cashnegativerealized0.0%Eversource paid GIP $233.0 million in the first nine months of 2026 and $141.3 million in the first nine months of 2025, reducing its…
liabilitypositiverealized0.0%Eversource paid GIP $233.0 million in the first nine months of 2026 and $141.3 million in the first nine months of 2025, reducing its…