AMI Deployment and Cost Recovery

EVERSOURCE ENERGY · 2026-11-06 · Importance 40 · Surprise 42

PURA rescinded CL&P’s interim AMI cost-recovery tariff framework on July 1, 2026, citing delayed implementation, the pending base distribution rate case, and legislation permitting securitization of AMI costs. CL&P filed AMI implementation and cost-recovery proposals with its rate case on July 14, 2026, seeking an accelerated deployment framework using proposed PBR capital funding and future securitization for incremental O&M and stranded legacy meter costs. CL&P witnesses subsequently estimated capital costs and operating expenses at $1.3 billion. PURA closed CL&P’s separate request to authorize an earlier physical deployment schedule and had not acted in the established docket; CL&P requested a determination by November 2026.