ENTERGY CORP /DE/ · 2026-11-02 · Importance 58 · Surprise 42
Entergy is progressing with its $2 billion Phase 1 accelerated resilience programs. Entergy Louisiana is working on a $270 million grid-resilience project near New Orleans that will replace more than 500 poles and other electrical infrastructure. Entergy New Orleans began a grant-funded grid-hardening project covering 94 poles and more than 1,900 customers, while the Department of Energy awarded Entergy utilities $14 million for dynamic line-rating technology across more than 1,000 miles of existing transmission lines in Arkansas, Louisiana and Mississippi.
Key facts
- Entergy Louisiana is working on a $270 million grid-resilience project outside New Orleans that will replace more than 500 poles and other electrical infrastructure.
- Entergy New Orleans broke ground on a grant-funded grid-hardening project to upgrade 94 poles and directly benefit more than 1,900 customers.
- Entergy said Phase 2 of its resilience program would be near the end of the outlook period at the earliest.