FCX · 10-Q · 2026Q2 · Full report

Kucing Liar Development

FREEPORT-MCMORAN INC · 2026-08-06 · Importance 58 · Surprise 42 · In source text

PTFI is developing the Kucing Liar deposit in Indonesia’s Grasberg minerals district, with ramp-up planned to begin around 2030 and design capacity of approximately 130,000 metric tons of ore per day. At June 30, 2026, PTFI had incurred approximately $1.4 billion for the development, with an additional estimated $4 billion of capital investments through 2033, averaging approximately $0.5 billion annually. At full rates, the deposit is expected to produce approximately 750 million pounds of copper and 735 thousand ounces of gold per year, supporting continuity of large-scale Grasberg production.

Key facts

Impact estimates

metricdirectionstageexpectedbasis
assetspositiveprobable+3.4%Capital investments for Kucing Liar are estimated to approximate an additional $4 billion through 2033, averaging approximately $0.5…
cashnegativeprobable-3.4%Capital investments for Kucing Liar are estimated to approximate an additional $4 billion through 2033, averaging approximately $0.5…
revenuepositivecontingentAverage annual Kucing Liar production at full rates would approximate 750 million pounds of copper and 735 thousand ounces of gold.
assetspositiveprobableKucing Liar ramp-up is planned to commence in the 2030 timeframe to a design capacity of approximately 130,000 metric tons of ore per day.