Microsoft reportedly withdrew from a planned data center project in Essex, where it had been expected to serve as Nscale’s anchor tenant. The project had faced delays and was described as being in limbo after Microsoft’s withdrawal. The report links the project to a broader £22 billion UK investment pledge, but does not specify the value of the Essex facility or the capacity affected.
Key facts
- Microsoft was to be the anchor tenant at Nscale’s first data centre in the UK as part of a broader pledge to invest £22bn in the UK, according to the report. source
- According to The Telegraph, Microsoft pulled out of a planned major data centre project in Essex that had faced delays and was in limbo. source
Impact estimates
| metric | direction | stage | expected | basis |
|---|---|---|---|---|
| cash | negative | contingent | — | Microsoft was to be the anchor tenant at Nscale’s first data centre in the UK as part of a broader pledge to invest £22bn in the UK,… |