NCLH · 10-Q · 2026Q3 · Full report

Ship Construction Commitments

Norwegian Cruise Line Holdings Ltd. · 2026-10-29 · Importance 64 · Surprise 42 · Matches filing data

As of September 30, 2026, Norwegian Cruise Line Holdings had 13 ships on order with combined contract prices of approximately €18.0 billion, or $20.4 billion. Its ship construction contracts totaled approximately $19.4 billion, with committed undrawn export-credit-backed facilities of approximately $10.8 billion expected to fund about 80% of those contracts. The commitments exclude the two Oceania Cruises Sonata Class ships scheduled for delivery in 2032 and 2035 and the Regent Seven Seas Cruises Prestige Class ship scheduled for delivery in 2033 from that 80% funding coverage.

Key facts

Impact estimates

metricdirectionstageexpectedbasis
cashnegativecommitted-72.2%As of September 30, 2026, the combined contract prices, including amendments and change orders, of the 13 effective ships on order were…