Regulatory Approval Milestones

NEXTERA ENERGY INC · 2026-09-09 · Importance 23 · Surprise 24

The West Virginia Public Service Commission rejected requests to delay evidentiary proceedings for NextEra Energy Transmission’s MidAtlantic Resiliency Link project. MARL is a 107.5-mile transmission line intended to address projected electricity-demand growth and emerging grid needs. Hearings remain scheduled for October 26 through November 2, 2026, moving the project toward a regulatory decision.