NI · 10-Q · 2026Q2 · Full report

Data Center Infrastructure Investment

NISOURCE INC. · 2026-08-05 · Importance 64 · Surprise 42 · In source text

NiSource estimates the aggregate cost of Contract Assets and Pool Resource Assets supporting existing data center customers at $9.25 billion to $9.75 billion. The company expects to invest approximately $600 million initially in Pool Resource Assets, incremental to previously disclosed data-center capital estimates. GenCo is developing a combined-cycle natural gas facility for the ADS Contract and combined 400 MW and 100 MW battery-energy-storage installations, with on-site construction activities expected to begin in the third quarter of 2026.

Key facts

Impact estimates

metricdirectionstageexpectedbasis
assetspositiveprobable+0.8%NiSource expects to make approximately $600 million of capital investments in connection with Pool Resource Assets initially being…
assetspositivecommittedGenCo mobilized in June 2026 for initial civil site work to support construction beginning in the third quarter of 2026 for its new…
cashnegativecommittedGenCo mobilized in June 2026 for initial civil site work to support construction beginning in the third quarter of 2026 for its new…
assetspositivecommittedGenCo awarded the battery equipment supply contract in February 2026 for a combined 400 MW and 100 MW BESS and anticipates on-site…
liabilitynegativecommittedGenCo awarded the battery equipment supply contract in February 2026 for a combined 400 MW and 100 MW BESS and anticipates on-site…