NI · 10-Q · 2026Q2 · Full report

Federal Power Act Emergency Order

NISOURCE INC. · 2026-08-05 · Importance 44 · Surprise 60 · In source text

NIPSCO received successive 90-day emergency orders under Section 202(c) of the Federal Power Act to keep the R.M. Schahfer coal facility operating through September 19, 2026. The orders state that continued operation is required to address an energy emergency in MISO’s North and Central regions and authorize cost recovery under 16 U.S.C. § 824a(c). NIPSCO filed a complaint with FERC seeking a MISO tariff mechanism to recover and allocate compliance costs and made two related filings with the Indiana Utility Regulatory Commission. Revenues and operating costs associated with the facility are subject to recovery under the emergency-order tariff and return to customers.

Key facts

Impact estimates

metricdirectionstageexpectedbasis
operating_incomenegativerealizedBefore planned retirement at end of December 2025, NIPSCO received successive 202(c) emergency orders to continue operating R.M. Schahfer…
operating_incomeunclearprobableNIPSCO filed a complaint at FERC seeking modification of the MISO tariff for recovery/allocation of costs to comply with the 202(c)…