Texas Large Load Regulation

NRG ENERGY, INC. · 2026-11-09 · Importance 40 · Surprise 42

Texas SB 6, signed June 20, 2025, establishes requirements concerning ERCOT planning and service for large loads of at least 75 MW, including interconnection, curtailment, co-location, forecasting, and transmission cost allocation. The PUCT adopted final rules on forecasting, co-location, and interconnection; on September 18, 2026, it adopted large-load interconnection standards that require financial security. The PUCT approved ERCOT revisions to its interconnection study process on June 18, 2026, while cost-allocation, rate-design, and curtailment rulemaking remained in progress. On August 3, 2026, the Texas governor directed verification and audits of data centers in the interconnection process, with ERCOT planning to file reports on batch-zero eligibility and community impacts in December 2026.