ORCL · News · 20260930N
Datacenter Capacity — Wisconsin
ORACLE CORP · 2026-09-30 · Importance 37 · Surprise 42 · In source text
Aterio reported a material risk that Oracle's Project Lighthouse campus in Port Washington, Wisconsin, will miss Oracle's second-half 2027 delivery guidance. The analysis indicated that meaningful electrical load may not be available until mid-2028, with separate reporting citing possible operational delays into early 2028 or April 2029. The delay risk was attributed to power-grid interconnection and regulatory issues involving American Transmission Co., increasing execution risk for the reported $15 billion Oracle/OpenAI complex.
Key facts
- The Port Washington data center complex is described as a $15 billion complex being built in partnership with Oracle and OpenAI. source
- Project Lighthouse in Port Washington, Wisconsin is a 1.3 GW data center campus being built for Oracle. source
- A report said Project Lighthouse completion could be pushed to early 2028 or even April 2029 due to power grid connection issues and regulatory hurdles with American Transmission Co. source
- Aterio sees a material risk Project Lighthouse will miss Oracle's second-half 2027 delivery guidance, with meaningful load unlikely before mid-2028. source
Impact estimates
| metric | direction | stage | expected | basis |
|---|---|---|---|---|
| assets | positive | probable | — | The Port Washington data center complex is described as a $15 billion complex being built in partnership with Oracle and OpenAI. |
| revenue | negative | contingent | — | A report said Project Lighthouse completion could be pushed to early 2028 or even April 2029 due to power grid connection issues and… |