ORCL · News · 20260930N

Datacenter Capacity — Wisconsin

ORACLE CORP · 2026-09-30 · Importance 37 · Surprise 42 · In source text

Aterio reported a material risk that Oracle's Project Lighthouse campus in Port Washington, Wisconsin, will miss Oracle's second-half 2027 delivery guidance. The analysis indicated that meaningful electrical load may not be available until mid-2028, with separate reporting citing possible operational delays into early 2028 or April 2029. The delay risk was attributed to power-grid interconnection and regulatory issues involving American Transmission Co., increasing execution risk for the reported $15 billion Oracle/OpenAI complex.

Key facts

Impact estimates

metricdirectionstageexpectedbasis
assetspositiveprobable—The Port Washington data center complex is described as a $15 billion complex being built in partnership with Oracle and OpenAI.
revenuenegativecontingent—A report said Project Lighthouse completion could be pushed to early 2028 or even April 2029 due to power grid connection issues and…