PEG · 10-Q · 2026Q3 · Full report

Capacity Market and Load Growth

PUBLIC SERVICE ENTERPRISE GROUP INC · 2026-11-02 · Importance 40 · Surprise 42

PJM filed in July 2026 for FERC approval of a Reliability Backstop Procurement to secure 15-year commitments from new generation matching the 2028/2029 delivery-year reliability shortfall; after FERC’s September order, PJM submitted a revised filing in late October seeking approval by January 29, 2027, and plans an auction for March 1, 2027 if approved. FERC rejected in October 2026 the principal components of PJM’s proposal to curtail new large-load customers, including data centers, during peak demand. Separately, FERC’s June 2026 order directed RTOs and ISOs, including PJM, to establish rules for future large-load connections, including study processes and allocation of transmission costs; PSEG says the outcomes and business impacts remain uncertain.