PNW · News · 20260804N

Capital Expenditure Program

PINNACLE WEST CAPITAL CORP · 2026-08-04 · Importance 58 · Surprise 42 · In source text

Arizona Public Service Company projects approximately $10.35 billion of capital expenditures from 2025 through 2028. Planned investment covers generation, transmission, and distribution infrastructure to support load growth and reliability in Arizona. Pinnacle West also plans to convert two retired coal units at the Cholla plant to natural gas by 2029. Major transmission projects and generation upgrades are intended to serve rising demand from data centers and manufacturing customers.

Key facts

Impact estimates

metricdirectionstageexpectedbasis
assetspositiveprobableThe company announced plans to convert two retired coal units to natural gas by 2029.
cashnegativeprobableThe company announced plans to convert two retired coal units to natural gas by 2029.