Targa expanded its intra-Delaware Basin NGL pipeline system through the Delaware Express project, which commenced operations in the second quarter of 2026. The planned Speedway NGL Pipeline will transport NGLs from existing and future Permian Basin plants to Targa’s Mont Belvieu fractionation and storage complex. Speedway is designed as approximately 500 miles of 30-inch pipeline with initial capacity of approximately 500 MBbl/d and expansion potential to 1,000 MBbl/d. The project is expected to begin operations in the third quarter of 2027.
Key facts
- Speedway NGL Pipeline announced September 2025 will be approximately 500 miles of 30-inch diameter pipeline with initial capacity ~500 MBbl/d expandable to 1,000 MBbl/d and is expected to begin operations in the third quarter of 2027. source
- Delaware Express intra-Delaware Basin NGL pipeline expansion announced February 2025 commenced operations in the second quarter of 2026. source
- Three months ended June 30, 2026 Logistics and Transportation NGL pipeline transportation volumes: 1,098.9 MBbl/d source
- Pipeline transportation and fractionation volumes benefited from higher supply volumes primarily from our Permian Gathering and Processing systems source
Impact estimates
| metric | direction | stage | expected | basis |
|---|---|---|---|---|
| revenue | positive | probable | — | Speedway NGL Pipeline announced September 2025 will be approximately 500 miles of 30-inch diameter pipeline with initial capacity ~500… |