Manufacturing Capacity Expansion
Targa Resources Corp. · 2026-11-05 · Importance 48 · Surprise 42 · In source text
Targa brought the 275 MMcf/d Falcon II plant in Permian Delaware and East Pembrook plant in Permian Midland online in the first quarter of 2026, followed by the 275 MMcf/d East Driver plant in Permian Midland in the second quarter. The 275 MMcf/d Copperhead plant in Permian Delaware is expected to start in the fourth quarter of 2026. Targa plans additional 275 MMcf/d plants Yeti, Yeti II, Copperhead II, Wrangler, Ranger and Ranger II, and a 265 MMcf/d Roadrunner III plant, with expected startup dates from 2027 through 2028.
Key facts
- Targa’s Copperhead plant, a 275 MMcf/d plant in Permian Delaware, was expected to begin operations in the fourth quarter of 2026. source
- Targa’s Yeti plant, a 275 MMcf/d plant in Permian Delaware, was expected to begin operations in the second quarter of 2027. source
- Targa’s Yeti II plant, a 275 MMcf/d plant in Permian Delaware, was expected to begin operations in the third quarter of 2027. source
- Targa’s Roadrunner III plant, a 265 MMcf/d plant in Permian Delaware, was expected to begin operations in the first quarter of 2028. source
- Targa’s Copperhead II plant, a 275 MMcf/d plant in Permian Delaware, was expected to begin operations in the first quarter of 2028. source
- Targa’s Wrangler plant, a 275 MMcf/d plant in Permian Delaware, was expected to begin operations in the second quarter of 2028. source
- Targa’s Ranger plant, a 275 MMcf/d plant in Permian Delaware, was expected to begin operations in the second quarter of 2028. source
- Targa’s Ranger II plant, a 275 MMcf/d plant in Permian Delaware, was expected to begin operations in the second quarter of 2028. source
Impact estimates
| metric | direction | stage | expected | basis |
|---|---|---|---|---|
| revenue | positive | committed | — | Targa’s Copperhead plant, a 275 MMcf/d plant in Permian Delaware, was expected to begin operations in the fourth quarter of 2026. |
| revenue | positive | committed | — | Targa’s Yeti plant, a 275 MMcf/d plant in Permian Delaware, was expected to begin operations in the second quarter of 2027. |
| revenue | positive | committed | — | Targa’s Yeti II plant, a 275 MMcf/d plant in Permian Delaware, was expected to begin operations in the third quarter of 2027. |
| revenue | positive | committed | — | Targa’s Roadrunner III plant, a 265 MMcf/d plant in Permian Delaware, was expected to begin operations in the first quarter of 2028. |
| revenue | positive | committed | — | Targa’s Copperhead II plant, a 275 MMcf/d plant in Permian Delaware, was expected to begin operations in the first quarter of 2028. |
| revenue | positive | committed | — | Targa’s Wrangler plant, a 275 MMcf/d plant in Permian Delaware, was expected to begin operations in the second quarter of 2028. |
| revenue | positive | committed | — | Targa’s Ranger plant, a 275 MMcf/d plant in Permian Delaware, was expected to begin operations in the second quarter of 2028. |
| revenue | positive | committed | — | Targa’s Ranger II plant, a 275 MMcf/d plant in Permian Delaware, was expected to begin operations in the second quarter of 2028. |