XOM · Earnings call · 2026Q3T · Full report
Golden Pass LNG Project Timing
ExxonMobil Holdings Corp · 2026-10-30 · Importance 46 · Surprise 42
Management said Golden Pass Train 1 had made good progress after ExxonMobil took over work following the bankruptcy of a contractor, and that lessons from the challenges were incorporated into plans for Trains 2 and 3. The company expected Train 2 to be substantially complete by December 2026, with commissioning to begin thereafter. It expected mechanical completion of Train 3 in mid-2027. Management said it felt good about the schedule and execution plans developed with remaining contractors and QatarEnergy.
Key facts
- ExxonMobil expects Golden Pass Train 2 to be substantially complete by December and to begin facility commissioning.
- ExxonMobil expects mechanical completion of Golden Pass Train 3 in mid-2027.